PROGRESS ON WELL REPLACEMENT

The District announced today it is making progress with the well replacement project started after the District’s top-performing well unexpectedly collapsed in August 2017 after 25 years of service.
Crews from Pacific Coast Drilling reached final depth for the new well — just under 1,500 feet — drilling and well construction are now complete with test pumping scheduled to begin January 29. Next, infrastructure work that includes piping, electrical service, and pump controls is expected to be completed by the end of March.
Well 7A, located at the Orchard Run Treatment Facility, sustained a cave-in of a well column at approximately 900 feet underground. Repair of the well was determined to be impossible. Well 7A was the District’s top-producing well, providing 30-40 percent of the District’s potable water. To meet water demands while the replacement well is under construction, the District increase production from its other wells and encouraged customers to make water-efficient choices.